The knockdown rebuild process in Sydney, step by step
If you love your street but not your house, a knockdown rebuild can feel like the obvious answer. Then the questions start. What happens first? When do we move out? How long will it all take?
A knockdown rebuild has more moving parts than building on a vacant block, but each one is manageable when it’s planned in the right order. Here’s how the process works, stage by stage, and roughly how long each part takes.
1. Deciding whether to renovate or rebuild
The first step is working out whether a rebuild is the right move at all. If the house needs structural work, new services and a different layout, renovating can cost a lot and still leave you working around the original house. If the bones are good and the layout mostly works, a large scale renovation may be the better option.
It’s also worth checking early whether your property sits in a heritage conservation area or is listed as a heritage item. That can affect whether the house can come down at all and which approval pathway applies. Your council’s planning certificate (known as a section 10.7 certificate) is a good place to start.
2. Pre-design: survey, concept and cost estimate
Once you’ve decided to rebuild, the work starts with your site. A detail and level survey records the block’s boundaries, levels, trees and surrounding buildings, which shapes everything that follows.
From there, a designer or architect develops the concept design around your brief and your block. At SLD Projects, this is also when we prepare a detailed cost estimate. It isn’t a rough quote. It’s a document of up to 40 pages that works through each part of the build, so you have the most accurate figure possible before committing to the next stage.
Approximate timeframe: 1 to 2 months. Changing the concept plans often at this stage can extend this, so it helps to have a clear brief.
3. Design and approvals
Next, the concept is developed into the drawings needed for approval. Depending on your site, this can involve a BASIX assessment, town planning advice, stormwater design, landscape design, and heritage or bushfire assessments.
In NSW, there are two main approval pathways for a knockdown rebuild:
- Complying development certificate (CDC). A fast-track approval for projects that meet set planning standards. It can be issued by your council or an accredited certifier, in as little as 20 days. It isn’t available for new homes in heritage conservation areas, and some other site constraints also rule it out.
- Development application (DA). Lodged with your council and assessed on its merits. This is the usual pathway where a site is in a heritage conservation area, or where the design falls outside the CDC standards. Assessment times vary between councils and projects.
Many streets across the Inner West are in heritage conservation areas, so it’s worth confirming the likely pathway early rather than designing around one and finding it’s the other.
Approximate timeframe: around 3 months of design, plus council assessment. We recommend allowing at least 6 months for this stage overall.
4. Pre-build: construction drawings and selections
While approvals are under way or once they’re in hand, the design is developed into full construction drawings. This brings in a geotechnical report, structural engineering, and electrical, lighting, air conditioning and services layouts, along with Sydney Water approval.
This is also when selections and finishes are made, from fixtures, appliances and windows through to tiles, flooring and the layouts of your kitchen, bathrooms and laundry. It can be the most enjoyable part of the process and the most demanding, which is why we work through it with you alongside our suppliers.
Resolving these decisions before construction is what keeps provisional sums and variations to a minimum later on.
Approximate timeframe: around 3 months.
5. Contract and preparing to build
With the design, approvals and selections settled, we prepare a detailed cost analysis that breaks the whole project down. Once you’re comfortable with it, the contract is signed. We use the Master Builders Association (MBA) contract.
The construction certificate and certifier approvals follow, and we prepare to start on site.
Approximate timeframe: 4 to 6 weeks.
6. Moving out, disconnection and demolition
This is the stage that sets a knockdown rebuild apart. Before demolition, you’ll need to move out, and the property’s services, such as electricity, gas, water and sewer, need to be disconnected or capped.
Many older Sydney homes contain asbestos. It needs to be identified before demolition and removed safely by a licensed removalist. The house is then demolished and the site cleared, ready for construction.
It’s worth planning your temporary accommodation early. Knowing the timing of each stage makes it much easier to line up a lease that covers the full build.
7. Construction
Once construction begins, our team manages the trades, materials and site so the work stays on track and matches what was agreed. Simon remains directly involved throughout, and you’ll receive regular updates through our online client portal, with progress photos and schedules, so you don’t have to chase for information.
How long construction takes depends on the size and complexity of the home, the site and the finishes. We’ll give you a realistic timeframe for your project during the cost estimate stage.
8. Handover and aftercare
Handover is when the keys come back to you and you can move into a home designed for your block. Our work doesn’t end there. Warranty applies from handover, and we return for a 12-month maintenance check.
How long does a knockdown rebuild take overall?
From initial design through to handover, most knockdown rebuilds take between 12 and 24 months, depending on the complexity of the project. Most of the time in a knockdown rebuild is spent before demolition. Design, approvals and pre-build planning typically take longer than many people expect, and that’s where a good result is set up. Rushing these stages is the most common reason builds run into delays and cost changes later.
Every project is different, but planning the full timeline from the start helps with everything from your temporary accommodation to your finances.